View Range

  • (associated Level: Base of Footings looking UP for Main floor, T.O. Sheathing main floor for Upper floor)
  • Top: Main Floor (T.O. Sheathing offset 0’6”)
  • Cut Plane (associated Offset 2’0”)
  • Bottom: greyed out
  • View Depth Level: Main Floor (T.O Sheathing offset 0’6”)

Cut Plane: cut through foundation walls looking up, set view limits high enough to see walls above

Visual Style: wireframe

Filters: primary framing, secondary framing

Phase Filter: Project Completion, New construction

Beams (tag as girders)

Headers over any large openings in foundation walls (tag as girders)

Supporting posts

Floor joists

Crawlspace access point (if through floor)

Floor sheathing (oval fill)

Hangers

Dimensions

¨  Cantilevers, from face of core of support to outside edge of framing

¨  Span of each framing rollout, including intermediate supports along the way

¨  Openings in floor, if any (such as stairs, crawlspace access, laundry chutes)

Labels

¨  Tag girder beams and headers

¨  Posts and post caps

¨  Existing framing rollouts

¨  New framing rollouts

¨  Floor sheathing thickness and nailing pattern

¨  Tag anchors and straps

¨  Note any joist rollout obstacles to avoid (toilet flanges generally)

¨  Hangers

Sheet Notes

¨  Fastener  schedule

¨  Framing Notes